Radiantly Done
Last week the plumbers were busy roughing in the sewer and water pipes before the foundation was covered with insulation and topped with wire mesh.
Under Slab
This week the plumbers dug trenches in the foundation so that sewer and water pipes could be set. As a result, we can begin to see
Backfilling
With the foundation walls poured and insulated, the crews are beginning to back fill the interior of the building.
|